Construction Update: The Mark 101 in Sage Hill – March 13-16, 2017

We completed framing of the second floor this week at The Mark 101 and we started the third.  We also had our make up air unit installed and some back fill on the west side of the building.

Working outside is much more pleasurable now with it warming up to +10 on Monday, March 15th and seasonable temperatures continuing throughout the week.

Here are some photos of our site progress:

March 13, 2017 – Make Up Air Unit Installation

March 15, 2017 – Framing Ongoing

3rd Floor Framing Ongoing

Concrete Slab Prep Above the MUA

East Elevation Site Progress

Framing Ongoing

March 16, 2017 – Sunny and warm today!

3rd Floor Framing Ongoing

Back Fill West Side of Building

Hallway Site Progress

Suite Site Progress

Suite Ceiling Site Progress

To find out floorplan availability of one bedroom, two bedroom and one bedroom plus den units per floor, please visit here.  We are now sold out of the B2 in the first of our three buildings being constructed, but we still have one bedroom models available in the B1 anc C1 models.

Construction photos showing the progress on The Mark 101 in Sage Hill are also available on our Facebook page in this album.

More updates coming soon.

For more information on The Mark 101 in Sage Hill please contact Dianne:

234

Sales Centre Location:  3727 Sage Hill Drive NW, Calgary

Show Suite Hours:  Monday – Thursday 2 – 8 pm;  Saturday, Sunday and Holidays:  12 – 5 pm

icon 2 1-403-536-2388

icon 2 info@themark101.com

icon 3www.themark101.com

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s