Construction Update: The Mark 101 in Sage Hill in Northwest Calgary

Nuovo by Shane Homes officially started construction on The Mark 101 in Sage Hill on August 17th, 2016 with grading of the site!

Since then we have been busy.  We will be sharing our construction progress as we go along in a blog and on our Facebook page in this album.

Sept 2014 – Before

August 17, 2016 – Site Grading

fullsizerender2

August 24, 2016 – Temporary Fencing South

temp-fencing-south-1

August 25, 2016 – Site Grading

August 29, 2016 – Building A Parkade Excavate Start & Site Servicing Stormceptor

September 1, 2016 – Site Servicing – Deep Service ADS Storm Tank & Deep Service Sage Hill Tie Ins

September 1, 2016 – Building A Bulk Excavation & Water from Well

September 8, 2016 – Civil Services

More updates coming soon!

 

5 responses to “Construction Update: The Mark 101 in Sage Hill in Northwest Calgary

  1. Pingback: Construction Update: The Mark 101 in Sage Hill in Northwest Calgary | Nuovo by Shane Homes·

  2. Pingback: Construction Update: The Mark 101 Condo in Sage Hill in Northwest Calgary – Oct 3 – 7, 2016 | Nuovo by Shane Homes·

  3. Pingback: Construction Update: The Mark 101 Condo in Sage Hill in NW Calgary – Oct 11 -19, 2016 | Nuovo by Shane Homes·

  4. Pingback: Construction Update: The Mark 101 Condo in Sage Hill in Northwest Calgary – Oct 20 – 26, 2016 | Nuovo by Shane Homes·

  5. Pingback: Construction Update: The Mark 101 in Sage Hill in NW Calgary – Oct 28 -Nov 2, 2016 | Nuovo by Shane Homes·

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s